title: Abra-cadabra! How’s that for a turn around?
description: The Mining and Minerals Southern region team successfully upgraded a magnet at Abra Mine, reducing processing interruptions and enhancing operational efficiency.
image: https://news.monadelphous.com.au/hubfs/Copy%20of%20HubSpot%20Blog%20Image%20(36)-1.png
---

[![Monadelphous](https://news.monadelphous.com.au/hs-fs/hubfs/Monadelphous%20Logo%20Horizontal%20Red%20and%20Black%20(CMYK).jpg?width=300&height=38&name=Monadelphous%20Logo%20Horizontal%20Red%20and%20Black%20(CMYK).jpg "Monadelphous")](https://news.monadelphous.com.au/)

- News 
    - [Around the Sites](https://news.monadelphous.com.au/around-the-sites)
    - [In the Loop](https://news.monadelphous.com.au/in-the-loop)
    - [On the Hook](https://news.monadelphous.com.au/on-the-hook)
    - [On the Wire](https://news.monadelphous.com.au/on-the-wire)
    - [Ramp Up](https://news.monadelphous.com.au/ramp-up)
    - [The Fix](https://news.monadelphous.com.au/the-fix)
    - [The Pipeline](https://news.monadelphous.com.au/the-pipeline)
- [Jobs with us](https://news.monadelphous.com.au/jobs-with-us)
- [Benefits](https://news.monadelphous.com.au/benefits)
- [Contact us](https://news.monadelphous.com.au/contact-us)

[![Monadelphous](https://news.monadelphous.com.au/hs-fs/hubfs/Monadelphous%20Logo%20Horizontal%20Red%20and%20Black%20(CMYK).jpg?width=300&height=38&name=Monadelphous%20Logo%20Horizontal%20Red%20and%20Black%20(CMYK).jpg "Monadelphous")](https://news.monadelphous.com.au/)

<https://news.monadelphous.com.au/the-pipeline/abra-cadabra-hows-that-for-a-turn-around#growfast-header__mobile-nav__mmenu>

[![Monadelphous](https://news.monadelphous.com.au/hs-fs/hubfs/Monadelphous%20Logo%20Horizontal%20Red%20and%20Black%20(CMYK).jpg?width=300&height=38&name=Monadelphous%20Logo%20Horizontal%20Red%20and%20Black%20(CMYK).jpg "Monadelphous")](https://news.monadelphous.com.au/)

- News 
    - [Around the Sites](https://news.monadelphous.com.au/around-the-sites)
    - [In the Loop](https://news.monadelphous.com.au/in-the-loop)
    - [On the Hook](https://news.monadelphous.com.au/on-the-hook)
    - [On the Wire](https://news.monadelphous.com.au/on-the-wire)
    - [Ramp Up](https://news.monadelphous.com.au/ramp-up)
    - [The Fix](https://news.monadelphous.com.au/the-fix)
    - [The Pipeline](https://news.monadelphous.com.au/the-pipeline)
- [Jobs with us](https://news.monadelphous.com.au/jobs-with-us)
- [Benefits](https://news.monadelphous.com.au/benefits)
- [Contact us](https://news.monadelphous.com.au/contact-us)

[![Monadelphous](https://news.monadelphous.com.au/hs-fs/hubfs/Monadelphous%20Logo%20Horizontal%20Red%20and%20Black%20(CMYK).jpg?width=300&height=38&name=Monadelphous%20Logo%20Horizontal%20Red%20and%20Black%20(CMYK).jpg "Monadelphous")](https://news.monadelphous.com.au/)

<https://news.monadelphous.com.au/the-pipeline/abra-cadabra-hows-that-for-a-turn-around#growfast-header__mobile-nav__mmenu>

- News 
    - [Around the Sites](https://news.monadelphous.com.au/around-the-sites)
    - [In the Loop](https://news.monadelphous.com.au/in-the-loop)
    - [On the Hook](https://news.monadelphous.com.au/on-the-hook)
    - [On the Wire](https://news.monadelphous.com.au/on-the-wire)
    - [Ramp Up](https://news.monadelphous.com.au/ramp-up)
    - [The Fix](https://news.monadelphous.com.au/the-fix)
    - [The Pipeline](https://news.monadelphous.com.au/the-pipeline)
- [Jobs with us](https://news.monadelphous.com.au/jobs-with-us)
- [Benefits](https://news.monadelphous.com.au/benefits)
- [Contact us](https://news.monadelphous.com.au/contact-us)

# Abra-cadabra! How’s that for a turn around?

[Projects](https://news.monadelphous.com.au/the-pipeline/tag/projects)

 26 Nov 2026

 1 Minute Read

Recently, our Mining and Minerals Southern region team completed a magnet upgrade at Abra Mine within a tight 72-hour shutdown, helping address regular interruptions to the site’s processing operations.

Metal coming up from the underground mine, including ground supports, was overwhelming the existing conveyor magnet and stopping operations an average of 60 times per shift.

Each stoppage required the metal to be cleared by hand, causing significant downtime.

The team’s scope involved removing the original magnet, modifying the existing plant to accommodate a larger, more powerful unit, and installing another structure to house an additional magnet.

With just six shifts to complete the shutdown works, preparation started well before mobilisation, with a preliminary site visit allowing the team to review the structural package, assess equipment and develop the installation methodology.

Getting critical equipment to the remote site was another consideration, and to ensure it arrived on time, Project Manager Jason Markwell and Senior Project Engineer Jason Ford loaded a trailer and drove from Bunbury to Abra, stopping overnight in Meekatharra while the crew flew directly to site.

Once on site, the team worked through the 3D model and installation plan together, which led to sorting and preassembling the structural components as much as possible before the shutdown began.

Working across day and night shifts, the crew completed the installation on schedule, with the full mobilisation covering pre-works, construction, commissioning and demobilisation within just seven days.

Supporting the delivery were Estimator and Support SME Graham Jones, SMP Senior Supervisor Michael Humphries and SMP Supervisor Russel Elson.

The team at Endurance Mining praised the crew’s professionalism and teamwork through feedback after completion and described the work as an ‘extremely well executed project’.

What another great example of teamwork, effort and genuine care put into a project across the business, well done!

![](https://22708561.fs1.hubspotusercontent-ap1.net/hub/22708561/hubfs/Copy%20of%20HubSpot%20Blog%20Image%20(36)-1.png?width=1200&length=1200&name=Copy%20of%20HubSpot%20Blog%20Image%20(36)-1.png)

![](https://22708561.fs1.hubspotusercontent-ap1.net/hub/22708561/hubfs/Copy%20of%20HubSpot%20Blog%20Image%20(38)-1.png?width=1200&length=1200&name=Copy%20of%20HubSpot%20Blog%20Image%20(38)-1.png)

![](https://22708561.fs1.hubspotusercontent-ap1.net/hub/22708561/hubfs/Copy%20of%20HubSpot%20Blog%20Image%20(37)-1.png?width=1200&length=1200&name=Copy%20of%20HubSpot%20Blog%20Image%20(37)-1.png)

## Leave a comment

<https://news.monadelphous.com.au/the-pipeline/revving-up-25-years-with-brian>

 Previous Post

Revving up 25 years with Brian

<https://news.monadelphous.com.au/>

 Click Here

 Go to Home Page

<https://www.facebook.com/sharer/sharer.php?u=https://news.monadelphous.com.au/the-pipeline/abra-cadabra-hows-that-for-a-turn-around> <https://twitter.com/intent/tweet?url=https://news.monadelphous.com.au/the-pipeline/abra-cadabra-hows-that-for-a-turn-around&text=Abra-cadabra!%20How’s%20that%20for%20a%20turn%20around> <https://www.linkedin.com/shareArticle?mini=true&url=https://news.monadelphous.com.au/the-pipeline/abra-cadabra-hows-that-for-a-turn-around> <https://pinterest.com/pin/create/button/?url=https://news.monadelphous.com.au/the-pipeline/abra-cadabra-hows-that-for-a-turn-around&media=&description=Abra-cadabra!%20How’s%20that%20for%20a%20turn%20around>

---

![Monadelphous Logo Horizontal Red and Black (CMYK)](https://news.monadelphous.com.au/hs-fs/hubfs/Monadelphous%20Logo%20Horizontal%20Red%20and%20Black%20(CMYK).jpg?width=300&height=38&name=Monadelphous%20Logo%20Horizontal%20Red%20and%20Black%20(CMYK).jpg)

<http://www.linkedin.com/company/monadelphous> <https://www.facebook.com/MonadelphousCareers> <https://www.youtube.com/@MonadelphousGroupLimited> <https://www.instagram.com/monadelphousgroup/>

```json
{
  "@context" : "https://schema.org",
  "@type" : "BlogPosting",
  "author" : {
    "@type" : "Person",
    "name" : "Communications",
    "url" : "https://news.monadelphous.com.au/the-pipeline/author/communications"
  },
  "dateModified" : "2026-11-26T08:00:21.252Z",
  "datePublished" : "2026-11-26T08:00:21.000Z",
  "headline" : "Abra-cadabra! How’s that for a turn around?",
  "image" : [ "https://news.monadelphous.com.au/hubfs/Copy%20of%20HubSpot%20Blog%20Image%20(36)-1.png" ],
  "mainEntityOfPage" : {
    "@id" : "https://news.monadelphous.com.au/the-pipeline/abra-cadabra-hows-that-for-a-turn-around",
    "@type" : "WebPage"
  },
  "publisher" : {
    "@type" : "Organization",
    "logo" : {
      "@type" : "ImageObject",
      "url" : "https://news.monadelphous.com.au/hubfs/Monadelphous%20Logo%20Horizontal%20Red%20and%20Black%20(CMYK).jpg"
    },
    "name" : "Monadelphous"
  }
}
```