I was proud to present the 68th M&IS Teamwork Baton award to the teams collaborating on the Geraldton Port Maximisation (PMAX) Project.
This is well deserved recognition for the Mining and Minerals Southern Region team, including RTW, and the Melchor team, joining forces to deliver a new facility for trucks to unload onto underground conveyors.
The PMAX project is an important part of the State Government’s initiative to increase the port’s capacity and cater for emerging industries. Across the project timeline, a major highlight was how well our teams, both on and off site, worked together to overcome challenges along the way and keep the project moving.
Pleasingly, the team maintained an excellent safety record despite multiple crews working in close quarters, within a confined, vertical work area.
Each team brought unique expertise to the project, demonstrating the breadth of capabilities we can draw on as a collective when delivering complex scopes of work.
Melchor did a fantastic job completing the earthworks and piling, laying the foundations for the new facility. RTW produced exceptionally high-quality steel fabrication and the MMS team successfully completed structural steel installation, shed cladding, rapid roller door installation, and the installation of the conveyor belt and sump pumps.
Other key milestones included lifting the 35-tonne switch room into position and installing the CV402 belt and associated pipework.
This project is a fantastic example of what we can achieve when we bring together the diverse capabilities within our business and work collaboratively.
Since 2018, the baton has travelled to 68 teams to acknowledge great examples of teamwork across the division.
If you know of a worthy nominee, please let us know at communications@monadel.com.au
-1.png?width=600&height=338&name=Copy%20of%20HubSpot%20Blog%20Image%20(29)-1.png)
Leave a comment